The Global Industrial process
Planning phase
There was limited planning involved as the layout was determined by the client and they provided a detailed floorplan.
Design & engineering process
Because the client had supplied a floorplan and design within their brief, Global had to check some crucial measurements on-site to ensure they were accurate and that everything fit within the space and enough clearances were left for forklift mobility, fire exits and doorways.
All dimensions and configurations were checked on the loading calculator to know what post and beam thicknesses were required to achieve 1000kg pallet space.
Delivery and installation process
There was a slight delay in the installation due to final engineer checks of the concrete floor.
Once that was approved, Global liaised with the installation crew in setting a new date and then arranged the delivery of goods to be on-site the day prior. Overall, the installation was completed in 4 days.